Request for Proposal (RFP)

EV Charging Station Installation – DOVER, TN

Proposal Deadline: November 17, 2026
Dover Inn Motel & Cabins – DCFC Design-Build RFP | Universal EV LLC

Project at a Glance

Design-build, turnkey DC fast charging at Dover Inn Motel & Cabins in Stewart County, Tennessee.

2 × 180 kW DC Fast Chargers

Dual-port dispensers; minimum 360 kW total station capacity

Complete Design-Build

Contractor supplies PE-stamped engineering, equipment, labor and permits

5-Year Warranty

Equipment, electrical/civil installation and engineering design

5-Year O&M + SLA

97% monthly uptime per port; quarterly preventive maintenance

Dover, Tennessee

Dover Inn Motel & Cabins — Stewart County

Open-Access Charging

OCPP 2.0.1, CCS1, contactless card, RFID and QR payment

Engineering design responsibility: No engineering drawings are provided for this project. The selected contractor must prepare the complete design packet, sealed by a professional engineer licensed in Tennessee. The Owner's conceptual layout is not a construction drawing.

Scope of Work

  • Complete site survey and Tennessee PE-sealed engineering design packet; no engineering drawings are owner-furnished
  • Minimum 2 dual-port DC fast charging dispensers, at least 180 kW each; all 4 ports capable of simultaneous charging
  • Cumberland Electric Membership Corporation (CEMC) coordination, utility service, transformer and all associated costs
  • Electrical distribution, civil works, foundations, trenching, paving, bollards and site restoration
  • At least 4 EV stalls, including 1 accessible stall with access aisle and accessible route
  • Permits, inspections, installation, network configuration, testing and commissioning
  • 5-year equipment/design/installation warranty, operations and maintenance, and SLA

Minimum Qualifications

  • Valid Tennessee contractor and required electrical classification licenses
  • Tennessee-licensed professional engineer to seal the design packet
  • Current EVITP certification for at least one lead electrician or superintendent
  • At least 2 years of DCFC installation experience and 3 completed project references
  • Demonstrated DCFC utility coordination and energization experience
  • Ability to deliver 5-year O&M/SLA and 24/7 English/Spanish driver support
  • Required insurance, including general liability and professional liability for design services

Key Dates

RFP Issue Date October 27, 2026
Pre-Bid Site Visit Available upon request
Questions Deadline November 10, 2026
Proposal Submission Deadline November 17, 2026
Anticipated Award December 16, 2026
Anticipated Construction Start March 1, 2027
Substantial Completion April 30, 2027
O&M / SLA Period Start At written commissioning acceptance

Questions & Proposal Submissions:

Universal EV LLC

📧 proposal@universalgreengroup.com

📞 (214) 989-4173

Submit questions in writing by November 10, 2026. Pre-bid site visits are available upon request.

Download the Full RFP

Review the complete design-build scope, equipment minimums, engineering deliverables, contractor qualifications, five-year service commitments, evaluation criteria and submission instructions.

Questions? proposal@universalgreengroup.com  |  Proposals valid at least 90 days  |  Site visit on request

How to Apply

Follow the three steps below to submit your proposal.

01

Download the RFP

Download and review the complete 18-page design-build RFP and project requirements.

02

Review & Prepare

Submit any questions by November 10, 2026, and prepare your proposal following Section 6.

03

Submit by November 17

Email your proposal to proposal@universalgreengroup.com by November 17, 2026. Follow the email subject format in Section 9.2.

Open to qualified contractors. State and/or utility incentive program requirements may apply; see Section 8 of the RFP. Contractor is responsible for complete engineering design, utility coordination, and all turnkey project costs.